Chuyển đến nội dung chính

Uninterruptible Power Supplies (UPS) checking with Power Quality Analyzer


No electricity provider can ensure that an electrical supply don’t have voltage and frequency variations. The possibility of faults occurring in users’ installations or in the public distribution system remains incontrovertible and unforeseeable. 

Since information technology (IT) installations are particularly sensitive to power supply oscillation and distortions, they typically rely on an uninterruptible power supply (UPS) to deduct. 

Some configurations even include a second UPS supplied by a separate feeder, and a standby generator that can be set to start automatically three minutes after detecting a power interruption.

If the danger from weather or other local occurrences is great enough, some facilities will manually switch over to backup generation, ahead of time.
a_typical_contingency_supply_system_for_important_installations
Figure 1 illustrates a typical contingency supply system for important installations.

To help your contingency supply systems function as designed, perform the following tests during installation and then periodically (monthly or quarterly, depending on contractual agreements) after the system is commissioned.

Checking installation phase are divided into two stages:
1. Pre-installation – check before connecting the main loads.
2. Combined – connect main loads and check while turn standby generator off and on.

Pre-installation

1. UPS functional and alarms checks
Purpose: Test the functions of UPS, LED display, and alarm messages.

2. UPS specification checks
Purpose: Test and measure UPS specifications
Procedure: Record voltage, current, real power, apparent power, power factor, voltage and current Total Harmonic Distortion (THD) at both the input and output.
Adjust the loads from 0 to 100% in 25% steps for balanced load checking. For unbalanced load checking, follow this load matrix:
Unbalanced_load_testing_sequence

3. UPS burn-in check
Purpose: Clarify the UPS system can operate at the rated load under ambient room temperature conditions.
Procedure: Load the UPS to rated load and operate for 8 hours to 24 hours, depending on contractual requirements. 
Burn-in_test_records

4. UPS step load and bypass loss transient tests
Purpose: Demonstrate the transient response of the UPS module.
Procedure: Measure UPS transient response for:
1) 0 % to 100 % to 0 % load steps
2) 0 % to 50 % to 0 % load steps
3) 50 % to 100 % to 50 % load steps
4) UPS running with loss of bypass mains
In the example demonstrated in Figure 4, the three phase voltage waveform hardly varied, despite the 100% change in load current.
Successful_UPS_step_load_test
Successful_UPS_step_load_test_2
5. UPS start and stop test
Purpose: Focus on correct operation when the UPS is switched on and off with full load.
Procedure: With the module running at 50% and 100% load, switch the inverter OFF and ON. Record transients, load voltage, load current, mains 2 current, and mains 1 current.

6. UPS full load battery discharge test
Purpose: Focus on correct UPS operation for 15 minutes at full load during a power failure.
Procedure: Measure battery cells before and after discharge using a battery monitoring system.

7. UPS loss and return of mains test
Purpose: Focus on correct operation during loss and return of the mains.
Procedure: Run module at normal load and switch the UPS main input ON and OFF. Record transients, load voltage, load current, and mains 1 current.

8. UPS loss and return of battery test
Purpose: Focus on correct operation during loss and return of UPS batteries.
Procedure: Run module at normal load and switch the UPS main battery breaker ON and OFF. Record transients, load voltage, load current and mains 1 current.

9. UPS load transfer test
Purpose: Focus on correct operation during load transfer.
Procedure: Run module at normal load and switch UPS OFF and ON until the load is on static bypass. This procedure is reversed from static bypass to UPS. Record load voltage, load current and bypass current.
step_load_test_1
step_load_test_2
10. UPS transfer to bypass and back test
Purpose: Focus on correct operation with external bypass.
Procedure: Transfer the load to external bypass and back to UPS. Record load voltage and load current.

Combined test
Connect the main loads and standby generator and repeat the same tests at 0% and 100% load conditions. Monitor transfer between the mains supply, UPS, and standby generator to ensure that transients and waveform distortion stays within acceptable limits.

Maintenance test
Conduct periodic (monthly) maintenance tests throughout the life of the contingency supply system. Follow the combined test procedure for everything except the standby generator—it only needs to be tested once a year.

Conclusion
Many tests are involved when commissioning and maintaining a contingency supply system. Many parameters (three phase voltage and current, power, power factor, harmonics and transients) must be logged simultaneously over 8 hours to 24 hours and documented in report format. Use a power quality analyzer with data logging and reporting capabilities (responsible for site assessment and installation) and the service team (post-sales maintenance) in this example. 

Nhận xét

  1. This is most informative and also this post most user friendly and super navigation to all posts.
    Power Logger

    Trả lờiXóa
  2. Thank you so much for giving this information to me.
    Temperature Recorder

    Trả lờiXóa

Đăng nhận xét

Bài đăng phổ biến từ blog này

Understanding phase noise in signal generators

Source:  http://www.testtek.com/en/detail-info.php?id=2151 Signal generators manufacturers set great store by specifying phase noise, such that, regardless of the application, phase noise is frequently taken as a proxy of the equipment's overall performance. However, phase noise performance might have little or no affect in some applications. For example, 'close in' phase noise creates problems when the signal generator is used as a local oscillator, limiting its sensitivity or impairing bit error rate (BER) performance if used as a clock. 'Far out' phase noise, on the other hand, affects wideband communications systems by raising the noise floor and limiting the reception of poor signals. Choosing a signal generator to match phase noise performance to the requirements of the application can be difficult as manufacturers often characterise phase noise performance at different carrier wave frequencies and at different offsets from the carrier signal. ...

What is Internet of Things (IoT)?

Source:  http://testtek.com/en/detail-info.php?id=2139 The  Internet of Things  ( IoT , sometimes  Internet of Everything ) is the network of physical objects or "things" embedded with electronics, software, sensors and connectivity to enable it to achieve greater value and service by exchanging data with the manufacturer, operator and/or other connected devices based on the infrastructure of International Telecommunication Union's Global Standards Initiative.  Internet of Things connect physically and remotely by individuals, for both public sector and private sector,  in the sense of a computer network grid, of a created electrical device that is in place, with economic benefit and potential usefulness.  Each thing is uniquely identifiable through its embedded computing system but is able to interoperate within the existing  Internet  infrastructure. Experts estimate that the IoT will consist of almost 50 billion obj...
Looking inside supercapacitors could help to build higher performing parts Researchers from the University of Cambridge, together with French collaborators based in Toulouse, have developed a method that allows the inside of supercapacitors to be viewed at the atomic level. The team says this approach could be used in order to optimise and improve the devices. By using a combination of nuclear magnetic resonance (NMR) spectroscopy and scales sensitive enough to detect changes in mass of a 1µg, the researchers could visualise how ions move around in a supercapacitor. They found that, while charging, different processes are at work in the two identical pieces of carbon 'sponge' which function as the electrodes. Dr John Griffin, a postdoctoral researcher in the Department of Chemistry, said: "[Supercapacitors are] much better at absorbing charge than batteries, but since they have much lower density, they hold far less of that charge. Being able to see wh...